EX-10.1
from 10-Q 3 pages Third Amendment and Extension to Letter of Intent Dated March 1, 2007 by and Between Fagen, Inc. and Akron Riverview Corn Processors, LLC
12/34/56
EX-10.17
from 10-K 3 pages Second Amendment and Extension to Letter of Intent Dated March 1, 2007 by and Between Fagen, Inc. and Akron Riverview Corn Processors, LLC
12/34/56
EX-10.16
from 10-K ~1 page Consent to Assignment and Assumption of Marketing Agreement
12/34/56
EX-10.15
from 10-K ~1 page Consent to Assignment and Assumption of Marketing Agreement
12/34/56
EX-10.3
from 10-Q 10 pages Distiller’s Grain Marketing Agreement
12/34/56
EX-10.2
from 10-Q 19 pages Amended and Restated Ethanol Marketing Agreement*
12/34/56
EX-10.1
from 10-Q 25 pages Phase I and Phase II Engineering Services Agreement* Between Akron Riverview Corn Processors, LLC and Fagen Engineering, LLC March 14, 2007
12/34/56
EX-10.20
from 10-K 92 pages Lump Sum Design-Build Expansion Agreement Between Little Sioux Corn Processors, LP (“Owner”) and Fagen, Inc. (“Design-Builder”) September 20, 2006
12/34/56
EX-10.2
from 10-Q ~10 pages Project: Little Sioux Corn Processors Change Order No: 1-1 4808 “F” Ave. Marcus, Ia. 50126 Date: July 17, 2006 Project No: 03-06 Ia Attn: Steve Roe Original Completion Date; September 1, 2007 Contract For: The Contract Is Changed as Follows: # Cost Description 1 $ 936,000.00 Ddg Storage Building Expansion, 125’ X 100’ by 39’ Eave. Per Our Proposal #06038-1 Dated 7/17/2006 $ 936,000.00 Total
12/34/56
EX-10.1
from 10-Q 6 pages Our Understanding Is the Project Will Consist of Installing Two New Concrete Silos With Integrated Day Bin, Scalping Floor, Grinding Day Bin, Four New Hammermills, and MCC Room to Be Constructed West of the Existing Concrete Corn Storage Silos. in Addition, the Existing Corn Silos Will Be Modified to Have a Flat Bottom, a New Ddg Receiving Filter Will Be Added Along With the Existing Ddg Building Being Expanded With an Additional Loadout Pit and Conveyors. McCromick Drawing F1, Revision 1dated 5/17/05 Forms the Basis for the Proposal. Based on the Information We Have Received, Fagen Engineering Proposes to Perform the Following Scope of Work for the Complete Electrical and Control Design: · Coordinate Electrical Requirements With McCormick Construction. · Field Verify Existing Conditions. · Size and Specify All Electrical Gear. · Size All Feeders. · Create One-Line Diagrams. · Design and Develop Grounding Drawings. · Design and Develop Underground Drawings. · Design and Specify All Lighting. · Revise Existing Grains P&ID to Include New Equipment. · Specify and Furnish 26 Speed Switches, 4 Speed Transmitters, 12 Level Switches, 4 Level Transmitters, and 2 Elevator Leg Monitoring System. · Design and Develop Instrument Loop Drawings. · Design and Develop Motor Control Elementary Drawings. · Furnish All Electrical Control Panels Containing the PLC Controls Hardware, Reversing Contractors for the Electric Gates, and All Communication Hardware (Excluding Cabling) to Interface the New PLC Control System to the Existing System. the Complete System Shall Consist of the Following: Cp-100 Is Located in the Process Server or MCC Room.]
12/34/56
EX-10.2
from 10-Q 9 pages The Associated General Contractors of America Agc Document No. 205 Standard Short Form Agreement Between Owner and Contractor
12/34/56
EX-10.1
from 10-Q 3 pages Settlement Agreement and Release of Claims
12/34/56
EX-10.1
from 10-Q 4 pages Lscp, Lllp Deferred Bonus Compensation Plan
12/34/56
EX-10.1
from 10-Q 53 pages Agreement Between Owner and Design/Builder on the Basis of a Stipulated Price
12/34/56
EX-10.1
from 10QSB 1 page Material contract
12/34/56
EX-10.12
from 10KSB 4 pages Term Note 4
12/34/56
EX-10.11
from 10KSB 2 pages Term Note 3
12/34/56
EX-10.10
from 10KSB 2 pages Term Note 2
12/34/56